PROJECT SCHEDULE
OCT 2026
OCTOBER 20
Receive General Contractor Proposals
NOV 2026
November 11
General Contractor Interviews (tentative date)
JULY 2026
JULY 13
(B1) Start Early Schematics
OCT 2026
OCTOBER 19
(B2) Start Final Schematic Design
FEB 2027
FEBRUARY 1
(B3) Start Design Development
JUNE 2027
JUNE 21
(C1) Start Construction Documents
NOV 2027
NOVEMBER 1
(C2) Start Bidding
JAN 2028
JANUARY 16
(C3) Start Construction (contingent upon financing)