Carriage Homes Begin

Carriage Homes Begin

Carriage Homes Begin About Carriage Homes A and B begin after the new wellness space is open and Independent Living Phase 1 is occupied. The old wellness building comes down first, then the new homes go up over parking. Expect fencing, dust containment, vibration...
Gate 1 Utilities and Roads in Place

Gate 1 Utilities and Roads in Place

Gate 1 Utilities and Roads in Place About Gate 1 is complete when all utilities are relocated, tested, and tied in, the temporary roads have done their job, and the new drive and lots are open. Nothing moves forward until this is true. Gate 1 releases the Health Care...
Health Center and Commons Begin

Health Center and Commons Begin

Health Center and Commons Begin About Construction starts on the new Health Center (32 assisted living, 24 skilled nursing, and 16 memory care residences) and the Commons renovation, which adds a Bistro, salon and spa, and updated staff offices. Expect barriers,...